Performance Analysis of Vertical Axis Wind Turbine (VAWT) on Building in Yogyakarta
15 February 2020
09:00:00
15:00:00
Yogyakarta
Vocational College UGM
UGM
Objective: Research about Ethernet cable and Power Distribution
The ethernet cable can be used to the requirement, because it's have 4 pair cable inside.
The location of each module is far enough, so it's can drained the power.
Ethernet cable is a cable that have 4-pair cable inside, in this research the monitoring module need 4 cable to connect each module with another, so in this internal research 2 Ma'ruf Shidiq (assistant) try to using ethernet cable to send the data and power to each module.
Using 12-volt for powering up the module can avoid the power draining.
Need to apply the system for another module.
 
 
 
Heri Galang, Baskoro Zulhilmi